Start of Production for VigdisGullfaks from Saga to Statoil

Start of Production for Visund

person Julia Stangeland
Production on Visund A began on 21 April 1999. The oil and gas are processed on the platform, after which the oil is sent to Gullfaks A and the gas to Kvitebjørn.
— Visund A is a semi-submersible integrated accommodation, drilling and processing platform. Photo: Kjetil Alsvik/Equinor.
© Norsk Oljemuseum

The Visund field and the Snorre field share several similarities: both produce and process their own oil, and in both cases the oil is transported by pipeline to Gullfaks A for storage and export. Both fields also have some subsea wells.

Another similarity – one they also share with several other fields and installations – is that they have been developed and modified in several stages and phases.

They also differ in some respects. While the Snorre field is equipped with two platforms, the Visund field operates with only one. And whereas gas from Snorre is reinjected into the reservoir, gas from Visund is produced and transported to shore by pipeline via Kvitebjørn.

The Visund field was discovered in 1986, and the plan for development and operation (PDO) was approved in 1996. Visund initially started oil production and was later expanded to include gas production.[REMOVE]Fotnote: «Visund» on Norwegian Petroleum. https://www.norskpetroleum.no/en/facts/field/visund/  Downloaded 19 December 2025.

The Visund field lies at a water depth of 335 metres, 26 kilometres northeast of Gullfaks A. Map: Norwegian Offshore Directorate.

Start of Production for VigdisGullfaks from Saga to Statoil
Published 19. December 2025   •   Updated 19. December 2025
© Norsk Oljemuseum
close Close